Planning Appeal Success Following Public Inquiry - Bewley Road, Angmering, West Sussex
Case study

Planning Appeal Success Following Public Inquiry - Bewley Road, Angmering, West Sussex

Gleeson Land appointed Mayer Brown at the earliest stage of site promotion to provide strategic flood risk and drainage advice for land at Bewley Road, Angmering, West Sussex. From the outset, the site presented sensitivities around flood risk, surface water management and downstream impacts. These were issues that ultimately became central to the planning and appeal process.

Transport Planning
Infrastructure Design
Environmental Assessment

Details

Trusted Technical Advice From Site Promotion to Appeal

Gleeson Land appointed Mayer Brown at the earliest stage of site promotion to provide strategic flood risk and drainage advice for land at Bewley Road, Angmering, West Sussex. From the outset, the site presented sensitivities around flood risk, surface water management and downstream impacts. These were issues that ultimately became central to the planning and appeal process.

Mayer Brown’s role went beyond technical compliance. We acted as a trusted advisor, helping the client understand risk, shape strategy and make informed decisions from first principles through to Public Inquiry.

“Mayer Brown’s early involvement gave us confidence the site could be promoted and, if necessary, defended at appeal. Their advice was grounded in experience and stood up to scrutiny.”

Gleeson Land

The Challenge

Flood risk and drainage were key planning considerations for the site and formed the basis of objection to the planning application. These issues were later pursued in detail by a Rule 6 party at appeal, placing the scheme under intense technical scrutiny.

At the same time, the site needed to demonstrate wider planning benefits (including biodiversity net gain and community infrastructure) within an ambitious promotion and planning timetable.

The challenge was not simply to prepare a drainage strategy, but to develop a solution that was:

  • Technically robust
  • Policy-compliant
  • Capable of securing stakeholder agreement
  • Defensible under cross-examination at Public Inquiry

Our Approach

Early strategic advice and site appraisal

Mayer Brown became involved immediately following exchange of the promotion agreement in January 2024. Our early appraisal assessed flood risk constraints, drainage feasibility and policy risk, allowing the client to proceed with confidence that the site could be promoted and ultimately defended.

This early input shaped the drainage strategy from the outset, ensuring it was proportionate, evidence-led and capable of withstanding future challenge, not just meeting minimum submission requirements.

 

Flood Risk Assessment and Drainage Strategy

We prepared a comprehensive Flood Risk Assessment and surface water drainage strategy, informed by detailed understanding of local catchment conditions, attenuation requirements and discharge controls. The strategy demonstrated that surface water could be managed sustainably without increasing flood risk on- or off-site.

Crucially, the approach anticipated the types of objections commonly raised at appeal, reducing the risk of late redesign or technical vulnerability. It meant also that there was no requirement for the Sequential Test because it was demonstrated the development would be safe for its lifetime and would not increase flood risk elsewhere. 

 

Proactive stakeholder engagement

Mayer Brown worked closely with the Lead Local Flood Authority (LLFA) throughout the process, responding constructively to technical queries and refining proposals where appropriate. This proactive, solution-focused engagement secured LLFA support for the drainage strategy prior to determination.

 

Planning application and appeal

A planning application was submitted in August 2024 and was recommended for approval by officers, subject to conditions. Despite this, the scheme was refused at committee.

Mayer Brown supported the subsequent appeal, acting as expert witness at Public Inquiry. Our flood risk and drainage evidence was challenged by a Rule 6 party, but we successfully defended the methodology, assumptions and conclusions through written evidence and cross-examination.

Because Mayer Brown had shaped the technical strategy from the earliest stages, there was full continuity between site appraisal, submitted evidence and inquiry testimony. This was a critical factor in maintaining credibility under scrutiny.

Outcome

  • Planning appeal allowed in December 2025 following Public Inquiry.
  • Flood risk and drainage strategy supported by the Lead Local Flood Authority.
  • Technical evidence successfully defended against Rule 6 challenge meaning no requirement for the Sequential Test.
  • Rapid progression from site promotion to consent within an ambitious programme.

Beyond technical matters, the scheme delivers wider planning benefits, including:

  • 20% biodiversity net gain, exceeding policy requirements
  • Land for a new purpose-built facility for Cancer United (an Angmering-based charity) supporting a locally rooted organisation with strong connections to the community

Why Mayer Brown

This project demonstrates Mayer Brown’s value as a trusted technical advisor — not just a technical author. By combining early strategic judgement, robust technical assessment and authoritative expert witness support, we helped de-risk a complex site and secure consent in the face of challenge.

Our experience allows us to anticipate issues before they arise, shape strategies that are appeal-proof, and provide clients with confidence that their schemes are deliverable, defensible and aligned with both policy and best practice.


Related content


Request callback

Please leave us your details and we will endeavour to call you back as soon as we can.

Request callback

Contact us for more information

Sign up to keep in touch

Visit our preference centre to sign up for our e-newsletter and update your preferences.

CQMS
Construction Line
Bloom
Mind
Woking Food Bank
bmtrada